⚡ Regulatory Guide · Part 2

DISCOM Application Process

The 7-step process from application submission to commissioning, including exact timelines and DISCOM obligations under RERC regulations.

📝

Step-by-Step Application Process

Regulatory sequence for RE grid interconnection

Procedural Framework

The interconnection of renewable energy systems to the DISCOM grid is governed by a strict, multi-stage regulatory protocol defined by the RERC. This framework ensures technical feasibility, transformer capacity management, and the safe deployment of grid-interactive infrastructure.

The sequence mandates strict turnaround times (TAT) for both the applicant and the DISCOM. Non-compliance with these statutory timelines by the DISCOM often results in "deemed approval" clauses, advancing the application to the subsequent stage automatically.

1

Prepare Your Application

Applicants must gather the necessary documentation and submit the interconnection application via the DISCOM's official online portal.

Required Data Inputs:

  • Existing K-Number (Utility Account Identifier)
  • Current Sanctioned Load / Contract Demand
  • Proposed Renewable Energy System Capacity (kW)
  • Selected Interconnection Framework (NM, NB, GNM, or VNM)
  • Developer Details (EPC Contractor or RESCO)

Mandatory Document Uploads:

  • Latest paid electricity bill
  • Technical specifications of the solar panels and inverter
  • Proof of registration fee payment
  • Identity Proof (PAN / Aadhaar). For corporate entities: General Power of Attorney or Board Resolution.
  • For VNM/GNM: A formalized sharing agreement executed on Rs. 100 non-judicial stamp paper detailing the exact credit allocation ratio.
Online submission on Discom portalUploads only — no physical copies
2

Submit Application & Pay Registration Fee

Submit through the Discom's web portal / mobile app or manually at the designated Discom office. The Discom will acknowledge receipt and assign a unique registration number for online tracking.

Mandatory: provide e-mail address and mobile number. All subsequent correspondence happens via email/SMS.

Acknowledgement issued immediately
3

Technical Feasibility Study by Discom

The Discom evaluates whether the local distribution infrastructure can support your RE system.

Special Exemption: Applications for domestic consumers up to 10 kW under NM/VNM/GNM are deemed technically feasible without requiring a formal study. Any required enhancement to the sanctioned load is executed automatically by the DISCOM.

⏱ 15 days (existing consumers/systems)⏱ 30 days (new consumers/systems for VNM/GNM)Deemed feasible if Discom doesn't respond in time
4

Receive Letter of Approval (LoA)

If feasibility is confirmed, the Discom issues an LoA via email/SMS/post. This serves as the statutory clearance to commence installation.

If documentary or technical deficiencies are identified, the applicant is granted 15 days to rectify them. Failure to resolve these within the timeframe results in application cancellation.

⏱ LoA within 30 days of application acknowledgementRejection must be in writing with reasons stated
5

Install the RE System

The renewable energy system must be fully installed within 180 days of receiving the LoA. Installation must strictly adhere to CEA, RERC, and IEC technical standards. Equipment must be pre-tested by the supplier with valid test certificates provided.

The consumer maintains liability for the system up to the Interconnection Point; the DISCOM assumes responsibility for infrastructure beyond that point, including the metering equipment.

⏱ 180 days from LoALoA deemed cancelled if not installed in time
6

Submit Installation Certificate

Upon mechanical and electrical completion, the applicant must submit the Installation Certificate to the DISCOM utilizing the prescribed format available on the official portal.

⏱ Discom has 15 days after this to complete all formalities
7

Connection Agreement, Meter Installation & Commissioning

Within 15 days of receiving the Installation Certificate, the DISCOM is legally obligated to execute the following:

  1. Execute Connection Agreement: Formal signing of the interconnection agreement governing the 25-year operational lifecycle.
  2. Meter Installation: Installation and cryptographic sealing of the Bi-directional Net Meter and/or RE Generation Meter (conducted jointly with the consumer).
  3. Final Commissioning: Authorization and energization of the renewable energy system for grid interaction.

Note: Consumers possess the right to procure their own compliant metering equipment, subject to testing and installation by the DISCOM.

⏱ Within 15 days of installation certificateEnergy accounting starts from date of grid connectivity

System is Live — Billing Begins

Your RE system is now grid-connected. Meter readings are taken monthly as per the regular billing cycle. The Discom's bill will separately show: generation recorded, units consumed, billing credit, and RPO generation units used.

🔗
For VNM/GNM — Additional connectivity timeline

Connectivity to consumer/system must be granted by the Discom within 30 days from the date on which the consumer/system is declared (or deemed) technically feasible.

Quick Reference: Timeline Cheat Sheet

MilestoneDeadlineConsequence if Missed
Technical feasibility study (general)15 days from ack.Deemed feasible
Technical feasibility (VNM/GNM — new consumers)30 days from ack.Deemed feasible
Issue Letter of Approval (LoA)30 days from ack.Discom in default
Intimation of deficiencies to applicant20 working days
Consumer to resolve deficiencies15 days from deficiency noticeApplication cancelled
Consumer to install RE system after LoA180 daysLoA deemed cancelled; re-apply
Discom to commission system after installation certificate15 daysDiscom in breach
VNM/GNM: Connectivity after feasibility30 daysDiscom in breach
Agreement termination notice (VNM/GNM)90 days prior noticeAgreement continues