Official Regulatory Guide · Updated 2025

Solar Net Metering &
Renewable Energy Connection Guide

A complete reference for consumers, vendors, and installers under the RERC Grid Interactive Distributed Renewable Energy Generating Systems Regulations 2021 (Third Amendment 2025) — applicable to Jaipur Discom (JVVNL) and Jodhpur Discom (JdVVNL).

Net Metering
Net Billing
Group Net Metering
Virtual Net Metering
BESS / Battery Storage
RESCO Model
Regulatory AuthorityRERC — Rajasthan Electricity Regulatory Commission
Jaipur OrderJPR-5-1219 · Dated 30/12/2025
Jodhpur OrderCOMML.JDP/1116 · Dated 01/01/2026
AmendmentThird Amendment Regulations 2025
Section 1

Applicable Discoms

These guidelines are separately issued by both Discoms under the same RERC framework

Jaipur Discom
Jaipur Vidyut Vitran Nigam Limited (JVVNL)
Order: JPR-5-1219 · 30 Dec 2025 SE(Comml): T.C. Singhal · Tel: 0141-2747041
Jodhpur Discom
Jodhpur Vidyut Vitran Nigam Limited (JdVVNL)
Order: COMML.JDP/1116 · 01 Jan 2026 CIN: U40109RJ2000SGC016483 · Tel: 0291-2742227
Governing Law
RERC Grid Interactive DREGS Regulations 2021 + Third Amendment 2025
Supersedes all prior Discom orders on Net Metering

For systems commissioned before 30 June 2021

Existing Net Metering connections under the 2015 Regulations shall continue under the 2015 framework for the duration of their connection agreement. Switchover to Net Billing or GNM/VNM is allowed only after terminating the existing connection agreement.

Section 2

Types of Arrangements Available

Choose the one that best fits your consumer profile and installation type

Net Metering (NM)

Net Metering Arrangement

Best for domestic consumers who want to offset their own electricity use

How it worksRE system connected on consumer side of the meter. Surplus exported to grid is adjusted against consumption in the same billing cycle.
Meter typeBi-directional Net Meter (records both import and export)
Domestic surplusPurchased at weighted avg. tariff of large-scale solar (≥5MW competitive bidding, last FY) + 25%
Non-domestic surplusLapses at end of billing period — no payment
Year-end creditUnadjusted domestic credits paid in cash by 1st month of next FY
Key benefitFull exemption from wheeling, banking, CSS & additional surcharge (self-owned)
Net Billing (NB)

Net Billing Arrangement

Best for those who want maximum revenue from solar generation

How it worksRE system connected on Discom side of the meter. All generation sold to Discom; consumer buys grid power at retail rate.
Purchase tariffWeighted avg. competitive bidding tariff (last FY, same technology) + 40% incentive
Billing formulaBill = Fixed Charges + (Units consumed × Retail rate) − (RE units × PPA rate) − Billing Credit
Billing creditCarried forward monthly; paid in cash by 15th May of next FY if unused at year-end
No Parallel Op ChargesNet Billing consumers are exempt from Parallel Operation Charges
Key benefitFull exemption from banking, wheeling, CSS, and additional surcharge
Group Net Metering (GNM)

Group Net Metering

Same consumer, multiple connections in the Discom area

How it worksSurplus from a single RE system (with Net Meter) is adjusted across multiple electricity connections of the same consumer
Priority listConsumer sets the sequence for energy allocation; can be revised once per FY (2-month advance notice)
ToD consumersExcess energy across time blocks treated as off-peak for settlement purposes
Capacity limitUp to 100% of cumulative sanctioned load of all participating connections
Parent/ChildConnection with RE system = Parent; other connections = Child
Key benefitDomestic consumers: fully exempt from all charges. Non-domestic self-owned: exempt from most charges.
Virtual Net Metering (VNM)

Virtual Net Metering

Multiple different consumers share benefits of one RE system

How it worksAll generation from a single RE site exported via RE/Gross Meter; benefits distributed among multiple participating consumers by agreed ratio
Share ratioFixed in MoU/Agreement on stamp paper; changeable once per FY with 2-month advance notice
Lead ConsumerOne participating consumer acts as nodal person for all Discom correspondence
ScopeAll consumers must be within the same Discom's area of supply
Capacity limitUp to 100% of cumulative sanctioned load of all participating consumers
100kW–1MW optionCan choose VNM or Green Energy Open Access (not both)

Important: Switching between arrangements

A consumer on Net Metering cannot move to Net Billing, GNM, or VNM without first terminating the existing connection agreement. A Net Billing prosumer cannot avail VNM or GNM.

Section 3

Eligibility Criteria

Who can apply and what conditions must be met

You ARE eligible if...

You are a consumer of electricity in Jaipur Discom or Jodhpur Discom's area of supply
Your electricity account has no pending arrears (or you have deposited disputed amount under Section 56)
You intend to install RE system of more than 1 kW capacity
Your installation is within 100% of sanctioned load / contract demand
The project capacity is up to 1 MW (for NM/NB/GNM/VNM)
RE system is located on consumer premises (or at approved alternate location for GNM/VNM)
Distribution transformer capacity is available (≤ 80% cumulative loading rule)

You are NOT eligible if...

You have pending electricity arrears (without dispute deposit)
You are already on Net Metering and want GNM/VNM without terminating first
You are a Net Billing prosumer seeking VNM or GNM
Your RE system exceeds 100% of your sanctioned load
The relevant distribution transformer is already at or above 80% capacity
You want to do third-party sale (only RESCO model permitted)
System capacity exceeds 1 MW (must use RERC RE Tariff Regulations 2020 instead)

Special Relaxation for Government Connections

Government connections may be permitted conditional participation even with pending arrears, subject to conditions set by the Discom. Government connections under VNM/GNM (self-owned or RESCO) are also exempt from Cross Subsidy Surcharge and Additional Surcharge.

Educational Institutions (Net Metering consumers)

Schools/colleges recognized by GoI/GoR under Net Metering may opt for Net Billing during any two months of a financial year, subject to prior intimation to the Discom before the commencement of such period.

Section 4

Capacity Limits & System Sizing Rules

Critical technical boundaries every installer must know

ParameterLimitNotes
Individual Consumer — Maximum RE Capacity100% of Sanctioned Load or Contract DemandMust also conform to RERC Supply Code 2021
Minimum RE Capacity> 1 kWApplies to all arrangements (NM, NB, GNM, VNM)
Maximum per arrangement (NM / NB / GNM / VNM)Up to 1 MWAbove 1 MW: governed by RERC Tariff Regulations 2020
GNM / VNM — Cumulative Capacity≤ 100% of total sanctioned load of all participating connectionsEach connection's eligible load = its own sanctioned load
Distribution Transformer LimitCumulative RE on a DT ≤ 80% of DT capacityException: HT consumers who installed DT themselves (no 80% cap)
HT Consumers (≥11 kV)May connect RE at LT Bus Bar SystemNet Meter / RE Generation Meter must be on HT side of consumer's transformer
DC CapacityNo restriction on DC capacity (modules)Only AC inverter output capacity is regulated
Peak AC Capacity (Inverter)Must not exceed contracted AC capacityExcess AC generation in any 15/30-min block lapses (NM/NB) or treated as deemed drawl (behind-meter)
Behind-Meter Systems (not opting NM/NB)Max 100% of Contract Demand (AC side)No energy to be injected into grid; inadvertent injection is penalized
Co-located Captive Plants (up to 1 MW)May opt these Regulations OR RERC Tariff Regulations 2020Option once exercised cannot be changed

VNM/GNM consumers with 100 kW–1 MW Contract Demand

These consumers have a choice: avail VNM/GNM under these Regulations, OR opt for Green Energy Open Access under RERC Green Energy Open Access Regulations 2025. Both cannot be availed simultaneously.

Section 5

Step-by-Step Application Process

Follow this sequence from installation planning to commissioning

1

Prepare Your Application

Fill the prescribed application form (Annexure II for NM/NB; Annexure IV-C1 for VNM; Annexure IV-C3 for GNM) along with required documents. For VNM — also include a signed sharing agreement (MoU) on stamp paper from all participating consumers.

Documents required: Latest paid electricity bill copy · Technical specs of RE system & inverter · Proof of payment of registration fee · General Power of Attorney / Board Resolution (for firms/companies) · ID proofs of all consumers (PAN / Aadhaar / EPIC).

Online or Manual submissionUploads only — no physical copies
2

Submit Application & Pay Registration Fee

Submit through the Discom's web portal / mobile app or manually at the designated Discom office. The Discom will acknowledge receipt and assign a unique registration number for online tracking.

Mandatory: provide e-mail address and mobile number. All subsequent correspondence happens via email/SMS.

Acknowledgement issued immediately
3

Technical Feasibility Study by Discom

The Discom evaluates whether the local distribution infrastructure can support your RE system.

Special Rule — Domestic ≤ 10 kW (NM/VNM/GNM only): Applications for domestic consumers up to 10 kW are deemed accepted without requiring a formal feasibility study. Sanctioned load enhancement, if needed, is carried out by the Discom automatically.

15 days (existing consumers/systems)30 days (new consumers/systems for VNM/GNM)Deemed feasible if Discom doesn't respond in time
4

Receive Letter of Approval (LoA)

If feasibility is confirmed, the Discom issues an LoA via email/SMS/post. This is the official green light to begin installation.

If deficiencies are found, you have 15 days to resolve them and notify the Discom. Failure to resolve = application cancelled (can re-apply after fixing).

LoA within 30 days of application acknowledgementRejection must be in writing with reasons stated
5

Install the RE System

Install within 180 days of receiving the LoA. The installation must comply with all technical standards (CEA, RERC, IEC standards). Equipment should be pre-tested by the supplier with test certificates provided.

Consumer is responsible for the system up to the Interconnection Point; Discom takes over responsibility beyond that (including meters).

180 days from LoALoA deemed cancelled if not installed in time
6

Submit Installation Certificate

After installation is complete, submit the installation certificate to the Discom in the prescribed format available on the Discom's web portal.

Discom has 15 days after this to complete all formalities
7

Connection Agreement, Meter Installation & Commissioning

Within 15 days of receiving the installation certificate, the Discom completes:

1. Signing of the Connection Agreement (25-year term) · 2. Installation and sealing of Net Meter / RE Generation Meter (jointly with consumer) · 3. Commissioning of the RE system

Tip: Consumers may purchase their own meter, which will then be tested and installed by the Discom.
Within 15 days of installation certificateEnergy accounting starts from date of grid connectivity

System is Live — Billing Begins

Your RE system is now grid-connected. Meter readings are taken monthly as per the regular billing cycle. The Discom's bill will separately show: generation recorded, units consumed, billing credit, and RPO generation units used.

For VNM/GNM — Additional connectivity timeline

Connectivity to consumer/system must be granted by the Discom within 30 days from the date on which the consumer/system is declared (or deemed) technically feasible.

Section 6

Application Fees, Security Deposits & Waivers

All financial requirements at the time of application

Registration / Application Fee

Connection TypeFee
LT Single Phase₹ 200
LT Three Phase₹ 500
HT — 11 kV₹ 1,000
HT — 33 kV₹ 2,000
EHT — 132 kV and above₹ 5,000

Security Deposit (per kW of RE capacity)

Consumer CategorySelf-OwnedRESCO-Owned
Domestic₹ 100/kW₹ 200/kW (double)
Non-Domestic & Others₹ 200/kW₹ 400/kW (double)
Security deposit bears no interest.

Fee Waivers for Domestic Consumers (PM Surya Ghar / 5 Lakh Homes Target)

Until the State Government's target of 5 lakh rooftop solar installations is achieved, the following are waived for domestic consumers under NM, VNM, and GNM: 1. Application/Registration Fee · 2. Security Deposit · 3. Meter Testing Charges · 4. Requirement of execution of Connection Agreement (NM only). Check with the Discom for current waiver status.

Section 7

Metering Arrangements

Types of meters, who installs them, and associated responsibilities

RE Generation Meter

What it measures

Total electricity generated by the RE system. Installed at the Interconnection Point of the RE system. Required for all arrangements.

Cost: Consumer's expense
Testing/maintenance: Discom's responsibility (cost borne by consumer)
Check meter: Consumer must install one at own cost (used if main meter fails)
Net Meter

For Net Metering arrangements

Bi-directional meter recording both import (from grid) and export (to grid). Located at the interconnection point as determined by the Discom.

Position: Consumer side of the consumer meter
Phase: Single-phase or three-phase as required
AMI: Must have RS-485 or higher communication port
Net Billing Meter

For Net Billing arrangements

RE Generation Meter records all generation. System is connected on the Discom side of the consumer meter — all power goes to grid first.

Position: Discom side of consumer meter
Basis of billing: Meter readings taken by Discom are final
Jointly sealed: Yes — both parties' representatives

Consumer's metering rights

The consumer may purchase the requisite meter themselves (from the market), but it must be tested and installed by the Discom. All meters must comply with CEA (Installation and Operation of Meters) Regulations 2006. Meters must be installed where Discom personnel can access them easily 24×7.

Defective meter procedure

Consumer must report meter failure to Discom in the specified format. During defect period: readings from Check Meter are used. If both Main and Check Meters are defective: provisions of the Electricity Supply Code apply for estimated billing.

Section 8

Billing Formulas, Settlement & Worked Examples

Understand exactly how your electricity bill is calculated

Net Billing — Bill Calculation Formula

Formula (Regulation 12.5.3)
Energy Bill = Fixed Charges + Other Charges & Levies
               + (EDL × TRST)
               − (ERE × TPPA)
               − Billing Credit

EDL = Gross units consumed from grid (consumer meter)
TRST = Applicable retail tariff for consumer category
ERE = RE generation units (RE Generation Meter)
TPPA = Competitive bidding tariff (last FY) + 40% incentive
Billing Credit = Carried-forward credit from previous months
Example: Net Billing Consumer (Commercial, 10 kW system)Illustrative values
Fixed / Demand Charges₹ 1,200
Other levies & duties₹ 180
Grid consumption (EDL) — 500 units × ₹ 7.50 (TRST)₹ 3,750
Less: RE generation (ERE) — 400 units × ₹ 3.80 (TPPA)− ₹ 1,520
Less: Billing credit brought forward− ₹ 200
NET AMOUNT PAYABLE₹ 3,410

* TPPA (3.80) = Competitive bid tariff + 40% incentive, fixed for 25 years. Actual tariff varies by FY bidding results.

Net Metering — Energy Accounting Rules

ScenarioDomestic ConsumerNon-Domestic Consumer
Export > Import in billing periodSurplus purchased at competitive bid tariff (≥5MW solar) + 25%. Credit adjusted in next billing cycle.Surplus lapses — no payment, no carry-forward
Import > Export in billing periodNet imported units billed at retail tariff. Billing slab based on total consumption from all sources (grid + solar).Net imported units billed at retail tariff. Billing slab based on total consumption from all sources (grid + solar).
Unadjusted credits at year-end (31 March)Paid in cash by Discom within 1st month of next FY, at same rate (+25% above bid tariff)Lapse — no payment
Example: Net Metering — Domestic Consumer (5 kW system)Illustrative values
Total consumption this month (grid + solar)300 units
Solar generation250 units
Export to grid120 units
Import from grid170 units
Net import billed (170 − 120 units credited)50 units
Fixed charges₹ 60
Energy charge: 50 units × ₹ 4.50₹ 225
NET BILL PAYABLE₹ 285

* Billing slab determined by total 300 units (not just 50 net units). If export had exceeded import, surplus credit would carry forward.

GNM & VNM — Energy Accounting Summary

Group Net Metering

Settlement Logic

1Surplus from the RE connection is first adjusted against its own consumption
2Remaining surplus allocated to child connections per priority list
3Still-remaining surplus purchased by Discom at bid tariff + 25% (domestic rule)
4Priority list changeable once per FY (2-month advance notice)
5If RE connection is disconnected, unadjusted credits paid at year-end after settling dues
Virtual Net Metering

Settlement Logic

1All generation exported to grid via RE/gross meter
2Generation credited to each participating consumer's bill in agreed ratio
3If credited quantum exceeds a consumer's consumption: surplus purchased at bid tariff + 25%
4Sharing ratio changeable once per FY (2-month advance notice, new MoU)
5If a participating consumer's connection is disconnected: unadjusted credits paid at year-end

Time of Day (ToD) consumers under GNM/VNM

Surplus solar generation in any ToD time block (peak/off-peak) is first adjusted against the same time block. Any remaining surplus is treated as if it occurred in the off-peak block. Settlement of excess goes from lowest to highest ToD tariff block.

Year-End Billing Credit Settlement (Net Billing)

Any billing credit remaining at the end of the settlement period (March 31) is paid by the Discom to the consumer in cash, latest by the 15th of May of the next financial year. If a consumer leaves the system, the available billing credit lapses.

What every bill must show (Regulation 12.4)

For all RE consumers, the Discom's bill must separately itemize: (a) RE generation meter reading with opening/closing balance (b) Units consumed with opening/closing balance (c) Billing credit with opening/closing balance (d) Generation units used by Discom for RPO compliance.

Section 9

Applicable Charges, Exemptions & Waivers

Which charges apply and which are waived for each arrangement type

Arrangement & OwnershipBanking ChargesWheeling Charges & LossesTransmission ChargesCross Subsidy Surcharge (CSS)Additional Surcharge
NM — Self-Owned (all categories)ExemptExemptExemptExempt
NM — RESCO-Owned (Domestic)ExemptExemptExemptExempt
NM — RESCO-Owned (Non-Domestic)ExemptExempt50% of Open Access CSS rate50% of Open Access rate (min ₹1.25/kWh)
Net Billing — Self or RESCO (all)ExemptExemptExemptExempt
GNM/VNM — Domestic (Self or RESCO)ExemptExemptExempt (incl. losses)ExemptExempt
GNM/VNM — Non-Domestic, Self-Owned (same premises)ExemptExemptExempt (incl. losses)ExemptExempt
GNM/VNM — Non-Domestic, Self-Owned (other location)Exempt11kV wheeling charges + losses applyExempt (incl. losses)ExemptExempt
GNM/VNM — Non-Domestic, RESCO-Owned (on premises)ExemptExemptExempt (incl. losses)50% of Open Access CSS50% rate (min ₹1.25/kWh)
GNM/VNM — Non-Domestic, RESCO-Owned (other location)Exempt11kV wheeling + losses applyExempt (incl. losses)50% of Open Access CSS50% rate (min ₹1.25/kWh)
Government connections (VNM/GNM — any model)ExemptExemptExemptExemptExempt

BESS Wheeling Charge Waiver (GNM/VNM systems)

Systems with Battery Energy Storage: BESS capacity ≥ 5% of solar → 75% waiver on wheeling charges · Each 1% BESS beyond 5% → additional 1% waiver (up to 30% BESS) · BESS capacity ≥ 30% of solar → 100% waiver on wheeling charges. Applies to both self-owned and RESCO-owned systems.

Parallel Operation Charges

RERC may periodically stipulate Parallel Operation Charges for NM, GNM, and VNM consumers (to cover balancing/banking/wheeling costs net of RPO benefits). These do NOT apply to Net Billing consumers. Systems behind the consumer's meter are also subject to these charges.

CDM (Carbon Development Mechanism) Benefits

All CDM benefits arising from RE generation are retained by the Discom. However, the entire CDM benefit must be passed on to consumers through the Annual Revenue Requirement (ARR).

Section 10

RESCO Model — Third-Party Solar Installation

For vendors who own and operate RE systems on behalf of consumers

What is a RESCO?

A Renewable Energy Service Company (RESCO) is a third-party entity that owns and operates the RE system on the consumer's premises (or elsewhere) and provides solar energy to the consumer under a commercial arrangement. The Discom itself may also act as a RESCO (treated as its other business).

Agreement Structure

Key Contractual Rules

RESCO enters into a direct commercial agreement with the consumer regarding payment for solar energy
The Discom's Connection Agreement (NM/NB/GNM/VNM) is signed between the Discom and consumer only — not a tripartite agreement
Disputes between RESCO and consumer are settled mutually — the Discom and RERC are not parties to such disputes
Discom shall not disconnect a consumer on grounds of a RESCO-consumer dispute
RESCO Key Obligations

What RESCO Must Do

Bears all costs of setting up the photovoltaic system including metering and interconnection
Pays for actual cost of service line modifications/upgrades if required
Complies with all technical and safety standards (CEA, RERC, IEC)
Obtains all environmental and grid-connection approvals before commissioning
Security deposit is double the normal consumer rate

Site leasing / Space rental

An eligible consumer may lease their rooftop space, land, or water bodies to a RESCO for setting up the RE system. For VNM: any land owner (even non-consumer) may lease space to a RESCO or Utility-Led Aggregator. The Discom has no role in the commercial lease arrangement between RESCO and site owner.

Section 11

Safety, Technical Standards & Grid Requirements

Mandatory compliance for vendors and installers

ParameterStandard/ReferenceRequirement
Inverter Efficiency & TestingIEC 61683 / IS 61683Compliance required for efficiency and measurements
Environmental TestingIEC 60068-2 (1,2,14,30)Cold, dry heat, temperature change, damp heat tests
Total Harmonic Distortion (THD)IEEE 519 / CEA 2013Individual harmonics < 3%; THD (voltage & current) < 5%
Voltage Operating WindowCEA Connectivity Regulations 201380% – 110% of nominal. Must isolate within 2 seconds.
Frequency TripCEA Connectivity Regulations 2013Trip within 0.2s if freq goes above 50.5 Hz or below 47.5 Hz
SynchronizationCEA Connectivity Regulations 2013Must not cause voltage fluctuation > ±5% at interconnection point
DC InjectionCEA Connectivity Regulations 2013< 0.5% of full rated output or < 1% of rated inverter current
Power FactorCEA Connectivity Regulations 2013When output > 50%: lagging power factor > 0.9
Anti-IslandingIEC 62116Must detect islanding and disconnect; IEC-62116 tests required
Short-term Flicker (Pst)IEC 61000 / CEA 2013≤ 1 (over 10-minute window)
Long-term Flicker (Plt)IEC 61000 / CEA 2013≤ 0.65 (over ~2-hour window)
Power Quality (output)EN 50160, Discom standardsTests required at commissioning; inverter must filter harmonics
Paralleling DeviceCEA Connectivity Regulations 2013Must withstand 220% of normal voltage at interconnection point
Overload / OverheatCEA Connectivity Regulations 2013Auto shut-off on overload or overheat; auto-restart when normal
Manual Isolating SwitchDiscom requirementVisible open/close indication; lockable open; accessible 24×7 to Discom
AMI on MetersCEA Meters Regulations 2006RS-485 or higher communication port mandatory on all meters

Key Safety Responsibilities of the Consumer

  • Consumer is solely responsible for any fatal or non-fatal accidents caused by back-feeding from the RE system when grid supply is off.
  • Any alternate energy source (battery/DG/backup) must be restricted to the consumer's network — must not extend to the Discom's LT grid.
  • In emergencies, the Discom has the right to disconnect the consumer's installation at any time.
  • The Discom may also disconnect the RE system if it causes power quality problems for other consumers, hazardous conditions, or emergencies.
Section 12

Behind-the-Meter RE Systems (Not Opting NM/NB)

For consumers who install solar but don't want to sell/export to the grid

Key Rules
Prior written intimation to Discom is mandatory (using Annexure-V format)
Maximum capacity: 100% of Contract Demand (AC inverter side)
No energy to be injected into the grid
Inadvertent injection will be penalized as per applicable Regulations
Excess AC generation in any 15/30-min block treated as deemed drawl from Discom
Penalties for Non-Compliance
Installing without prior intimation: additional fixed charges levied for the entire period of installation until Discom discovers it
Existing installations (pre-2021) not intimated within 3 months of notification: additional monthly charges levied
Discom may inspect and verify installations at any time under the Act

For existing behind-meter solar consumers (pre-Sept 2021)

If you installed a Solar Rooftop PV system behind your meter without opting for Net Metering, you must submit the intimation form (Annexure-V) to the Discom. Failure to do so results in retroactive fixed charges. DC capacity is unrestricted — only the AC inverter output is regulated.

Section 13

Connection Agreements — Key Terms

Legal framework governing your RE connection

Agreement TypePartiesStamp PaperDurationTermination
Net Billing Agreement (Annexure IV-A)Consumer + DiscomStandard25 yearsMutual consent
Net Metering Agreement (Annexure IV-B)Consumer + DiscomStandard25 years (or as per pre-2021 agreement)Mutual consent
VNM — CAPEX Agreement (Annexure IV-D, B.1)Eligible Consumers + DiscomRs. 100/- non-judicial, notarized25 years or license validity90-day notice by any party (to Lead Consumer)
VNM — RESCO Agreement (Annexure IV-D, B.1 RESCO)RESCO + Discom + ConsumersRs. 100/- non-judicial, notarized25 years or license validity90-day notice by any party (to RESCO + Lead Consumer)
GNM — CAPEX Agreement (Annexure IV-D-1)Consumer (Parent) + DiscomRs. 100/- non-judicial, notarized25 years or license validity90-day notice (to Parent Consumer)
GNM — RESCO Agreement (Annexure IV-D-1 RESCO)RESCO + Discom + ConsumerRs. 100/- non-judicial, notarized25 years or license validity90-day notice by any party

What every agreement must cover

  • Technical and interconnection requirements (CEA, RERC standards)
  • Automatic isolation on grid power outage
  • Discom access to metering and disconnecting means — 24×7
  • Mutual indemnification for negligence/misconduct
  • Commercial settlement as per RERC Regulations
  • Synchronization circuit details, protection diagrams, test certificates
  • Consumer responsibility for all approvals and clearances

VNM-specific: Lead Consumer duties

  • Must be a participating consumer in the VNM arrangement
  • Signs the Net Metering agreement on behalf of all participating consumers
  • Acts as nodal person for all Discom correspondence
  • Any change in Lead Consumer must be communicated in writing with approval from all participants
  • May sign sharing ratio change documents on behalf of all consumers
Section 14

Penalties & Dispute Resolution

Consequences for non-compliance and how disputes are settled

For Consumers

  • Installing behind-meter system without intimation → Fixed charges for entire period of installation
  • Failing to intimate existing behind-meter installation within 3 months → Additional monthly fixed charges from month 4 onwards
  • Injecting energy into grid from behind-meter system → Penalty as per applicable Regulations
  • Failing to commission within 180 days of LoA → LoA deemed cancelled; fresh application required
  • Failing to remove deficiencies within 15 days → Application cancelled

For the Discom

  • Failure to complete technical feasibility study within 15/30 days → Proposal deemed technically feasible
  • Failure to issue LoA within 30 days of application acknowledgement → Discom is in default
  • Failure to complete commissioning within 15 days of installation certificate → Discom in breach
  • General failure to meet Regulation requirements → Penalty as decided by RERC from time to time
Dispute Resolution Mechanism

How billing and other disputes are resolved

Step 1: Billing disputes are first escalated to the Consumer Grievance Redressal Forum of the Discom.

Step 2: If unresolved, the consumer may approach the Electricity Ombudsman.

For RESCO-Consumer disputes: Resolved mutually between the consumer and RESCO. The Discom and RERC are not parties. The Discom shall not disconnect a consumer because of a RESCO dispute.

Arrears with dispute: Consumer may deposit the disputed amount with the Discom under Section 56 of the Electricity Act 2003, after which the Discom must allow NM/NB/GNM/VNM connection pending resolution.

Section 15

Quick Reference: Timeline Cheat Sheet

All critical time limits at a glance

MilestoneDeadlineConsequence if Missed
Technical feasibility study (general)15 days from ack.Deemed feasible
Technical feasibility (VNM/GNM — new consumers)30 days from ack.Deemed feasible
Issue Letter of Approval (LoA)30 days from ack.Discom in default
Intimation of deficiencies to applicant20 working days
Consumer to resolve deficiencies15 days from deficiency noticeApplication cancelled
Consumer to install RE system after LoA180 daysLoA deemed cancelled; re-apply
Discom to commission system after installation certificate15 daysDiscom in breach
VNM/GNM: Connectivity after feasibility30 daysDiscom in breach
Discom pays year-end billing credit (Net Billing)15th May of next FYDiscom in default
Discom pays year-end NM domestic creditFirst month of next FYDiscom in default
Existing behind-meter consumer intimation3 months from notificationRetroactive fixed charges
Change sharing ratio (GNM/VNM) — advance notice2 months before FY startChange not processed
Priority list change for GNMOnce per FY, 2-month advance noticeChange not processed
Agreement termination notice (VNM/GNM)90 days prior noticeAgreement continues
Jaipur Discom (JVVNL)
Regd. Office: Room 229, Vidyut Bhawan, Jyoti Nagar, Jaipur – 302005
Email: secomml@jvvnl.org · Tel: 0141-2747041
CIN: U40109RJ2000SGC016486
Jodhpur Discom (JdVVNL)
Regd. Office: New Power House, Jodhpur – 342 003
Email: seracommiju@gmail.com · Tel: 0291-2742227
Web: energy.rajasthan.gov.in/jdvvnl · CIN: U40109RJ2000SGC016483
Disclaimer
This guide is compiled from official Discom orders for informational purposes. Always refer to the original orders (JPR-5-1219 and COMML.JDP/1116) and RERC Regulations for legal accuracy. Tariff rates change with each FY competitive bidding cycle.