🚧 Field Troubleshooting

Application to Subsidy: 10 Common Blockers

Between submitting your PM Surya Ghar application and receiving the subsidy, there are 10 common issues that delay or derail projects. From portal login failures and DISCOM feasibility rejections to vendor non-compliance and subsidy payment failures — here is how to resolve each one systematically.

Issue 1: Portal Login OTP Not Received

Cannot log in because OTP never arrives
CauseResolution
Aadhaar mobile number doesn't match current SIMUpdate at nearest Aadhaar centre. Takes 24–48 hrs.
DND (Do Not Disturb) is enabledDial 1909 to disable immediately.
SIM inactive or expiredRecharge SIM or visit telecom store to reactivate.

Issue 2: Stuck at DISCOM Feasibility

Approval pending for weeks
TimelineAction to Take
After 20 DaysCall local DISCOM office, quote application number, request status.
After 30 DaysContact the DISCOM nodal officer designated for PM Surya Ghar.
After 45 DaysCall national helpline at 15555. File formal grievance on portal.

Issue 3: Feasibility Rejected (Insufficient Load)

Requested solar size exceeds sanctioned load
Warning: Installing solar panels before DISCOM feasibility approval will permanently disqualify your application from the PM Surya Ghar subsidy.
ProblemResolution
Applied for system larger than sanctioned loadComplete load extension application at DISCOM office before reapplying. See Load Extension Guide.

Issue 4: Consumer Category Non-Residential

Connection is classified as commercial or agricultural
ProblemResolution
Subsidy requires domestic/residential connectionApply for category change at SDO office with property proof and Aadhaar. Takes 15–30 days. Reapply on portal once corrected.

Issue 5: Vendor Not Available or Unresponsive

Cannot find a vendor, or vendor is delaying work
ProblemResolution
No vendors visible in your districtCheck latest vendor list on portal. Contact State Nodal Agency for offline vendor contacts.
Assigned vendor is unresponsiveFile a complaint on portal for vendor reassignment. Do not make advance payments without a written timeline.

Issue 6: Non-DCR or Non-ALMM Panels Installed

Wrong panels void your subsidy permanently
Critical: Verify ALMM listing at almm.mnre.gov.in before installation. Replacing panels after installation is expensive.
Verification StepDetails
Check ALMM RegistryVerify panel model and manufacturer at almm.mnre.gov.in.
DCR CertificateDemand DCR certificate from vendor mentioning "Domestic Content Requirement".
BIS MarkCheck for IS 14286 certification mark on every panel.

Issue 7: Geo-Tagged Photos Failing Upload

Portal rejects photos during commissioning
ProblemResolution
GPS/Location services disabledEnable GPS before opening camera app. Take photos outdoors.
File size too largeKeep each photo under 5 MB.
Missing metadataUse default camera app, not third-party apps like WhatsApp.

Issue 8: Net Meter Inspection Delayed

System installed but DISCOM hasn't inspected
TimelineAction to Take
After 15 DaysCall DISCOM with application number. Request inspection date and get ticket number.
After 25 DaysEscalate to DISCOM nodal officer. File written complaint with ticket number.
AlternativeSome states allow buying an approved private meter for DISCOM to install. Check state policy.

Issue 9: Commissioning Report (PCR) Rejected

PCR rejected by portal or DISCOM
Common ReasonsResolution
Serial numbers mismatchEnsure panel serials in photos match portal entries exactly.
Missing safety photosMust upload earthing, LA, and DC disconnect switch photos.
Name mismatchConsumer name on portal must match electricity bill name. See Name Change Guide.

Issue 10: Subsidy Not Credited

System commissioned but money hasn't arrived
Normal subsidy disbursement takes 30–60 days after commissioning. If delayed beyond this:
StepActionDetails
1Check PortalStatus should show "Subsidy Approved" or "Payment Initiated".
2Verify BankEnsure bank account is Aadhaar-seeded via NPCI mapper. Name must match perfectly.
3Raise GrievanceFile on portal with application number, commissioning date, and bank details.
4Call HelplineCall 15555, reference grievance number, ask for disbursement date.
5Email MNREEmail mnre.pmsg@gov.in with all details and passbook copy.

Vendor Verification Checklist

Verify before you pay
ItemVerification Details
RegistrationVendor is registered on PM Surya Ghar portal for your district.
QuotationIncludes detailed breakdown (panels, inverter, mounting, wiring, GST).
ALMM & DCRPanels listed on ALMM. DCR certificate provided.
AgreementWritten timeline, system specs, warranty terms, and penalty clause included.
AMCComprehensive maintenance agreement (5+ years) included in package.
PaymentAdvance payment does not exceed 50%. Remaining 50% payable after commissioning.

Official Sources & Related Guides

Useful links for further reading
ResourceDescription
PM Surya Ghar Portal ↗Application status, vendor list, grievance filing.
ALMM Registry ↗Verify approved solar panel models.
National Helpline: 15555Toll-free helpline for queries and complaints.
Name Change GuideFix DISCOM name mismatches.
Load Extension GuideFix insufficient load feasibility rejections.
KYC Mismatch GuideFix Aadhaar, PAN, and Bank mismatches.

Frequently Asked Questions

Common queries about project execution
How long does the entire process take?

Typically 3–6 months. Feasibility (15–20 days), vendor install (30–45 days), net meter (15 days), commissioning (7–15 days), and subsidy disbursement (30–60 days). Delays can extend this to 8–12 months.

Can I change my vendor after the application is approved?

Yes. Go to your application dashboard, select "Change Vendor," and choose from available registered vendors. Takes 5–10 working days and does not reset your application.

What if the subsidy amount credited is less than expected?

Subsidy is calculated based on actual installed capacity, not applied capacity. E.g., applied for 5 kW but installed 3 kW = subsidy for 3 kW. Verify slabs. If still incorrect, raise a grievance on the portal.

Still Stuck? Talk to Our Solar Experts

Our team can help you navigate DISCOM issues, vendor problems, and subsidy delays. Get Expert Help →